Why does it take so long?
Many frustrations occur with delays in projects and progress
in the downtown. It seems like it
always takes a long time to get anything done. The problem is a function of the process and how the process
is processed.
Working as a private sector representative to a public
sector process is sometimes confusing and drawn out. A Main Street Manager is sometimes confronted with issues
that never seem to go away because it just takes too long to get things
done. The problem is not one thing
but can be a number of things and how they relate to the process.
If there is a project that needs government approvals there
are a whole plethora of items that will dictate the time that it takes to
complete a task. The Borough or
City Council only meets a finite number of times as a group and if you have a
meeting after that time you need to wait until the next meeting.
If there is a need to get planning commission approval for
an item, it will be necessary to meet the planning commission and Borough or
city council. If that meeting that follows the planning commission requires
some formal action like a public hearing, then upon approval of the planning
commission there will he an advertisement posted concerning the hearing. The meeting will have to be advertised
for two weeks to provide notice to the community in case anyone wants to come
and support or oppose the project.
There is always the potential for a project to need approval
by a third party like the commonwealth or the county and you will need to meet
on their administrative timetable.
This timetable is a little more complex because you are dealing with
schedules and minds of, in many cases, long-term employees that are not as
flexible as you would like.
Using the above scenario let postulate the following
circumstance….someone comes to your group and says “guess what kids, my rich
uncle Yahootie died and left me some cash and I want to donate 20 benches to
the downtown.” The group say’s
“yeah let’s do it”.
Your main street lies on a state road and you will need to
get permission from Penn Dot to put a structure in the right of way. Say The Commonwealth comes back and
says you need a Highway occupancy permit (HOP). You must then locate where the benches will be on a scale
drawing.
So the group figures that since they are maybe 8 to weeks
out perhaps it is best to run the approval process in tandem with the planning
commission and the commonwealth application being done during the same time
frame. The n perhaps you find out
that the borough or the city would rather you have permission from them before
you apply to the commonwealth, just so everyone is on the same page.
Luckily, you can get on the agenda for the next planning
commission meeting with what could be as little as two weeks advance notice…but
they also want to see a scale drawing.
So you find someone who can provide the drawing but you missed your
window of two weeks prior to the meeting.
(Drawing 2 weeks).
You submit the drawing a few days after the last planning
commission meeting. You then wait 4 weeks for the meeting (Planning Commission
– 4 weeks).
When you get to the Planning Commission some attorney that
opposes anything that is ever proposed gets up and scolds the committee for
encouraging ne’er-do-wells to hang out downtown. He seems to have a concern on his part that the homeless
will live on the benches. The
planning commission recommends the plan but you could add an additional 4 weeks
if they need to check some of the fine points of the argument against you.
The planning commission then writes a letter to the council
supporting the application and that triggers your meeting with the borough or
city council. In most cases it
will be a meeting that takes place not at the next meeting but the following
meeting because it takes time to compose the letter and send to the council. (2
weeks to send the letter).
When you time arrives in front of council, you are 12 weeks
into the process and they like the idea no matter what the angry attorney from
the neighborhood says to the contrary. They say okay and apply for the
HOP.
It then takes you like 12 weeks to get it through the
process and because you are on fire
with your progress you get positive results that will get you through at
the end of 26 weeks.
The you order the benches and they come in say….4 weeks and
are installed within 4 weeks. You
are at 34 weeks under the best possible circumstance. If the time lines do not
match and you have 6 weeks on items instead of 4 weeks it will slip by quickly. Beware it is easy to get lulled into
acceptance of the a week here and a week there throughout the process…hours
turn into days, days to months and months to years.
If there is a question by the angry attorney that needs
review add 4 weeks for the next meeting.
If the angry attorney wants to talk legalese and you need the solicitor
to look at the project, add another 4 weeks. If the benches are on a grade
greater than 2 % look for delays while the Penn Dot people check you
handicapped accessibility and add another 12 to 26 weeks for a determination.
It would be nice if when someone gifted the organization
money and wanted to put an amenity on the streetscape. If it was easy cause you
just could order the amenity and then install it. But alas it is not
like that. What it is like has
built in delays to assure conformity and safety.
This project illustrates why in the revitalization process
you must go what I call “wide” .
have a lot of projects working all at once and go as quickly as you can
on all fronts. This will enable a
group to see progress and accomplishments because once the queue is set the
projects will proceed in rapid order even if they are caught up in the
procedural process for a extended period of time.
The more you do, the more you will have to do and the more
you will accomplish. If you wait
for one thing to be done before you start the next you will be doomed.
No comments:
Post a Comment